Construction Notice: Featherstone Road Construction

Featherstone Road:

FEATHERSTONE ROAD CONCRETE REPAIRS FROM DR. MLK, JR BLVD TO OPDYKE ROAD
GENERAL DESCRIPTION OF PROPOSED WORK PLAN AND SCHEDULE
Eastbound Lanes—
Week of April 24, 2020 –Miscellaneous preparations, MISSDIG marking utilities
Week of May 4, 2020 – Lane closures, Marking areas for replacement and removing and replacing poor concrete areas, this work is anticipated to take 25 work days
JUNE 1, traffic will be placed on eastbound lanes, while the above tasks are performed on the Westbound lanes.
It is anticipated that all pavement repairs on Featherstone will be completed by June 30, 2020
There may be some minor delays as some intersections on the North side of the street may be closed for a short time.
Inclement weather may affect our progress and hence the schedule may be altered.